Project Name:  Consulting Services for Railway Connectivity Improvement Preparatory Facility Project
Year: January 2023–Jun 2025 (On-going) 
Location: Bangladesh
Client: ADB
Main Project Features: The objectives of the consultancy service are to conduct the feasibility study, detailed design, bidding document and preparation of the Development Project Proposal (DPP) for total 11 sub-components of various sections and types for Bangladesh Railway, including the preparation of core and non-core business plan, and the land use master plan with digital data base for the land use of Bangladesh Railway (BR) land. Strategy for land development with project implementation methodology for BR's unused land will be proposed.
Position Held: Property Development Specialist
Activities Performed:
Prepare the land use master plan with digital data base for the land use of BR land. Priority development sites surrounding the major stations will be selected for project implementation planning and financial analysis. Strategy for land development with project implementation methodology for BR's unused land including TOD type development will be proposed for short-term and medium-term. 

Project Name: The Project for Capacity Enhancement for Transit-Oriented Development (TOD)
Year: July 2022–Jun 2025 (On-going) 
Location: Philippines
Client: JICA
Main Project Features: A technical cooperation project of JICA for capacity building and preparation of TOD (Transit Oriented Development) guideline, TOD planning method, and TOD implementation method in the Philippines. The counterpart is Base Conversion and Development Authority (BCDA). During the project implementation, two BCDA owned sites for TOD development will be selected, and the project will support BCDA to prepare the TOD project tenders by providing the above-mentioned tasks including major parameters, terms and conditions (PTCs) for the TOD project tenders.
Position Held: TOD Project Implementation Planning
Activities Performed:
Prepare TOD project implementation plans for the selected two sites (BGC station area and Senate DepEd station area) including project structuring, real estate market research and marketing, product development and integration, project phasing, implementation schedule, procurement method and conditions, revenue and cost estimation, financial model building, and financial and project evaluation, including the major PTCs for the TOD tenders. 

Project Name: JABODETABEK Urban Transportation Policy Integration Project Phase 3 (JUTPI-Phase 3)
Year: Apr 2022–Jun 2025 (On-going) 
Location: Indonesia
Client: JICA
Main Project Features: A technical cooperation project of JICA for capacity building and preparation of TOD (Transit Oriented Development) guideline, TOD planning method, and TOD implementation method in KABODETABEK area (Greater Jakarta Area). During the project implementation, several pilot sites for TOD development will be proposed by different local government bodies including DKI (Jakarta Special Province) in KABODETABEK, and a TOD project implementation plan will be prepared for each selected pilot site on the basis of the guideline and the methods prepare in this technical cooperation project.
Position Held: Project Implementation Planning Specialist
Activities Performed:
Prepare TOD project implementation plans for selected pilot sites (Urban center type, suburban type and transportation hub type) including project structuring, real estate market research and marketing, product development and integration, project phasing, implementation schedule, procurement method and conditions, revenue and cost estimation, financial model building, and financial and project evaluation.

Project Name:  FY 2021 Information Collection Study on TOD and Redevelopment of Residential Complex
Year: Aug 2021–Jan 2022
Location: Indonesia
Client: Urban Renaissance Agency of Japan (UR)
Main Project Features: Conduct pre-FS on TOD development planning and redevelopment of residential complex which the public housing agency of Indonesia is aiming for several existing sites which are owned by the public housing agency sites on the basis of collaboration agreement between UR and the public housing agency
Position Held: Project Scheme Development and Financial Specialist
Activities Performed:
Based on the current outline plan which the public housing agency prepared, revise the project scheme, estimate revenue and project cost based on the current market price researched and revised property product mix, and conduct financial analysis and project evaluation including the financial model building.

Project Name:  North–South Commuter Railway Extension (NSCR-EX) Project (Malolos–Clark) (Solis–Calamba) General Consultant Service
Year: Oct 2019–Dec 2023 (On-going) 
Location: Philippines
Client: Department of Transport, Government of Philippines
Main Project Features: Tender preparation and supervision of construction and procurement of the Malolos-Clark section of the North-South Commuter Railway project in Metro Manila Region currently in progress on the basis of doner finance from JICA and ADB. The O&M portion of the NSCR project is scheduled to be procured in a PPP O&M concession tender which is now being prepared by the transaction advisory team of ADB.
Position Held: Finance and Business Management Advisor
Activities Performed:
To estimate the O&M cost of the entire NSCR project on behalf of the client to be used as a public sector comparator, and support the client in preparation of contract management plan of the PPP O&M concession contract in terms of how the asset management system works and how relevant information are generated among sub-systems of urban railway, together with the transaction advisor. 
In addition to that, various supporting activities for the client and the transaction advisor with regards to the O&M operational and technical and asset management related requirements for the PPP O&M concession tender are being conducted.

Project Name:  Strengthening of Management Ability of Operation and Maintenance Company for the Opening of Railway Line1 in Ho Chi Minh City
Year: Dec 2017–Dec 2022 (On-going)
Location: Vietnam
Client: JICA
Main Project Features: A technical cooperation project to strengthening the management ability of the O&M company for the opening of Urban Railway Line 1 in Ho Chi Minh City which is under progress based on JICA finance. Various capacity building and training are being conducted by JICA consultant team to the staff of HURC1 (the O&M company for the Line 1) for the opening and the sustainable O&M operation of the Urban Railway Line 1.
Position Held: Business Method / Information Collection and Analysis Specialist 
Activities Performed:
•As a member of the regulation team, support the client in preparing the necessary regulations and drafting the O&M contract by drafting fere setting policy, regulatory and institutional framework of the Urban Railway operation, drafting a O&M contractual framework, conducting a series of seminars to the important stakeholders of Line 1 construction and operation with regards to the O&M contract related issues (still on-going).

Project Name: Yangon Urban Mass Rapid Transit Construction Project
Year: May 2018–Dec 2019
Location: Myanmar
Client: JICA
Main Project Features: To select a priority section of east-west line and north-south line of Yangon MRT network, and conduct a detailed feasibility study for JICA ODA loan fir construction. When JICA ODA loan is decided, the project would move to detailed design phase of the priority section on grant basis.
Position Held: Regulatory Framework/Organization / Funding Scheme Specialist
Activities Performed:
To propose an implementation framework including regulatory framework for Yangon YUMRT project and prepare funding, construction, and O&M scheme of the project including TOD urban development along the corridor.

Project Name:  Preparatory Survey for Phnom Penh Urban Railway Development Project
Year: Sept 2017–Nov 2019
Location: Cambodia
Client: JICA
Main Project Features: To conduct a feasibility study for construction and operation of AGT system along the priority corridor in Phnom Penh.
Position Held: Project Implementation Method and PPP Applicability Analysis
Activities Performed:
To conduct PPP applicability of the project and propose appropriate implementation method for the project.
To prepare a financial model for both AGT and TOD urban development along the corridor, and conduct impact analysis of the total regional development including value capture benefit.

Project Name:  Ho Chi Minh City Underground Commercial Mall and Park Development
Year: Feb 2017–Oct 2017
Location: Vietnam
Client: Private Vietnamese Company
Main Project Features: A development of underground commercial mall/ park and underground major road along the Saigon River in the urban core area of Ho Chi Minh City in which several underground metro lines and major underground stations are being planned. The development would link the stations with underground and at grade commercial malls.
Position Held: Project Structuring and Financial Evaluation Specialist 
Activities Performed:
Based on the basic design of the development prepared by technical and architecture design teams, conduct the preparation of the project implementation plan which includes project phasing, integration of public and private project components, forecasting of revenues and costs of relevant components, financial model structuring and financial evaluation of the entire development which includes both public and private, and PPP project components.

Project Name: KPPIP (The Committee for Acceleration of Priority Infrastructure Delivery)/ MPA (Metropolitan Priority Area) Support Facility 
Year: May 2014–Aug 2019 
Location: Indonesia
Client: JICA
Main Project Features: The key objectives of the project are 1) To promote priority infrastructure development including selected projects from Indonesia-Japan framework through sustainable operation of KPPIP PMO, 2) Realization of priority infrastructure development including selected projects from Indonesia-Japan framework
Position Held: Pre-FS and PDF (Project Development Facility) Specialist
Activities Performed:
Infrastructure Policy Advisory: Supporting the development of availability payment system (APS) in Indonesia and supporting the development of ministerial regulation on AP.
Pre-FS (OBC) and PDF (FBC): Executing OBC supplementary study for Jakarta Sewerage (Zone1), and Bali Sports Complex project including Value for Money (VFM) analysis for funding scheme decision.
Monitoring and Debottlenecking: Executing debottlenecking activities for priority infrastructure projects (incl. HVDC, SUMSEL 8-10 etc.). In addition, developing guidelines for OBC check, project monitoring and debottlenecking.
OBC and PDF Evaluation (incl. conducting Pre FS of different PPP projects)
Conducted Pre-FS and PDF Facility for priority infrastructure projects, and delivered policy proposal on infrastructure finance.

Project Name:  Operation and Maintenance Consulting Services (OMCS) for Project of Jakarta Mass Rapid Transit System Phase I Lebak Bulus – Bundaran Hotel Indonesia 
Year: Nov 2016–May 2019
Location: Indonesia
Client: MRTJ (MRT Jakarta)
Main Project Features: To provide necessary technical support to the operation company of the first MRT line in Jakarta during its preparation period and up to 6 months after the commencement of the operation. Support includes preparation of internal rules and guidelines for operation and management, capacity building and training of MRTJ staff including drivers, basic design of company IT system and necessary cost estimation of operation and management of MRTJ.  
Position Held: O&M Cost Estimation Specialist 
Activities Performed:
Provided cost estimation of required operation, maintenance and management of MRTJ for preparation and operation of MRT system, and prepared a basis for initial year budgeting, financial support system and financial modeling.

Project Name: Preparatory Survey for Lebak Bulus Station Area Development Project 
Year: Sep 2013–Aug 2015
Location: Indonesia 
Client: JICA
Main Project Features: Transit Oriented Development (TOD) including public infrastructure (bus terminal, park & ride facilities, station plaza and pedestrian deck) and commercial infrastructure (hotel, apartment, shopping mall and office building) co-located with newly developed Lebak Bulus MRT station.
Position Held: PPP Scheme Development Specialist 
Activities Performed:
Developed financing scheme for the project in a PPP format combined with the government support. Conducted financial analysis and risk analysis based on the scheme,  and proposed primary security package.

Project Name:  Preparatory Survey for Phnom Penh Urban Railway Development Project
Year: Sep 2017–Aug 2018
Location: Cambodia
Client: JICA
Main Project Features: To conduct a technical and financial feasibility study on development of the first Mass Transit Transport (Automated Guideway Transit: AGT) in Phnom Penh, including basic designing of the AGT system, financial and economic evaluation, assessment of PPP application in the project.
Position Held: Business Scheme / Financial Analysis Specialist 
Activities Performed:
Developed financing scheme for the project in a PPP format combined with the government support.